(2-minute read)
Workers build foundation forms around reinforcing steel at the Killam Elementary School site on Nov. 13 as a dump truck delivers fill. Photo from the Killam Project website.
Construction of the new Killam Elementary School made substantial progress over the past month on both site preparation and foundation work, according to a Nov. 13 project update from the Town of Reading. The project is moving from heavy excavation into active foundation construction at the school’s Charles Street site.
Excavation around the building footprint
Crews continued extensive excavation around the building footprint, including the areas planned for the loading dock and generator enclosure. Crews removed unsuitable soils, previously disturbed materials, and large boulders, hauled them off site, and stockpiled suitable material for reuse.
Trucks continued delivering structural fill and removing excavated soil and debris to keep both excavation and foundation work moving.
Crews set forms and reinforcing steel for the new Killam Elementary School’s foudnation on Nov. 10. Photo from the Killam Project website.
Foundation work advances
Foundation construction advanced significantly during the month. Work included surveying, laying out footings, installing forms, placing reinforcing steel, and pouring concrete. Crews also installed geotextile fabric, crushed concrete, and stone to create stable foundation surfaces.
Managing groundwater and quality
Groundwater management remained active throughout the month, with Liquid Resources Technology monitoring and adjusting the site’s temporary water management system as needed.
Concrete forms and reinforcing steel wait beside the foundation work on Nov. 16, with the site’s temporary water management system in the background. Photo from the Killam Project website.
Environmental monitoring, testing, and inspection also continued, including soil evaluations, compaction testing, reinforcing steel inspections, and concrete quality as the project shifts into its next phase.
Where the project stands
The November progress follows a busy October. According to Town Manager Jayne Wellman’s October report, the town participated in the Massachusetts School Building Authority (MSBA) construction kickoff, and the town issued the foundation permit by mid-October.
The October report also noted that the construction bid came in nearly $25M below the projected budget used in the MSBA agreement. The Killam School Building Committee voted to pursue rescinding more than $14M in borrowing authorization at Town Meeting, with final amounts depending on how closely the owner’s project manager’s projections align with the MSBA’s revised financing calculations.